The final few steps in Hg CEMS implementation
We are working on the last few steps to complete the project.
Thermo sent us a mercuric choloride generator for a game cube probe but we have the modified inertial probe installed so we had to wait a couple of months for the right kit. We are scheduled to have it installed the week of the 14th. If all goes well that will be the last piece of hardware to install.
We have tentatively scheduled a 30A RATA test for the last week of January. This will of course not be for official certification but GE is obligated to perform the test in order to prove out the system.